COMPARISON OF WHAT IF, FAST TRACK, AND CRASH PROGRAM METHODS FOR ACCELERATION OF PROJECT DELAY

Authors

  • Ratih Prawirawati Universitas Brawijaya
  • Agus Suharyanto Universitas Brawijaya
  • Alwafi Pujiraharjo Universitas Brawijaya

DOI:

https://doi.org/10.21776/ub.rekayasasipil.2022.016.02.5

Keywords:

crash program, fast track, delay, acceleration, what if

Abstract

One of the obstacles that often arises in working on a project is project delay. Delays are usually caused by unplanned obstacles  or problems. Delays cause the project implementation duration is not as planned in employment contract. What If, Fast Track, and Crash Program methods can all reduce project delays. The costs incurred by the Fast Track method and the What If method were less than the realization costs, while the Crash program method is greater than the realization costs, but the costs of all these methods are greater than the planning costs.The combination of Fast Track Crash Program methods and the combination of Fast Track What If methodsboth can restore the initial duration of the project.If the methodsare reversed into combinations of the Crash Program Fast Track methods and What If Fast Track methods, the produced results aredifferent, namely unable to restore the initial duration of the project. The costs incurred from these combinations are both less than the realization costs, but still higher than the planning costs.

References

Alifen, R. S., Setiawan, R. S., & Sunarto, A. Analisa "What If" Sebagai Metode Antisipasi Keterlambatan Durasi Proyek. Dimensi Teknik Sipil , I (2). (1999).

Tjaturno, & Mochtar, I. B. Pengembangan Metode Fast-Track Untuk Mereduksi Waktu Dan Biaya Pelaksanaan Proyek Studi Kasus Rumah Menengah Di Malang, Jawa timur. Media Komunikasi Teknik Sipil , Tahun 17 (1). (2009).

Kumalasari, V. Penerapan What-If Analysis Pada Sistem Penunjang Keputusan Dalam Menentukan Program Diet. Jakarta: Fakultas Ilmu Komputer Universitas Indonesia. (2008).

Husain, A. Manajemen Proyek. Yogyakarta: Andi Offset. (2011).

Soeharto, I. Manajemen Proyek (Dari Konseptual Sampai Operasional). Jakarta: Erlangga. (1995).

Downloads

Published

2022-06-30

How to Cite

Prawirawati, R., Suharyanto, A., & Pujiraharjo, A. (2022). COMPARISON OF WHAT IF, FAST TRACK, AND CRASH PROGRAM METHODS FOR ACCELERATION OF PROJECT DELAY. Rekayasa Sipil, 16(2), 101–109. https://doi.org/10.21776/ub.rekayasasipil.2022.016.02.5